Waste Water Engineering Ventilating shafts are provided to a sewer line at every 300 m 150 m 200 m 100 m 300 m 150 m 200 m 100 m ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Dilution method of disposing of sewage, is not preferred to When diluting water is used for water supply near the point of sewage disposed When diluting water has high dissolved oxygen content When the diluting water is having flow currents When sewage is fresh When diluting water is used for water supply near the point of sewage disposed When diluting water has high dissolved oxygen content When the diluting water is having flow currents When sewage is fresh ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering It is customary to design a sewer for D.W.F. on the basis of Thrice the average demand Four times the average demand Twice the average demand Average demand Thrice the average demand Four times the average demand Twice the average demand Average demand ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The sewerage system originates from House sewers Lateral sewers Branch sewers Main sewers House sewers Lateral sewers Branch sewers Main sewers ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The design period in years for pumping plants, is 5 to 10 2 to 3 1 3 to 5 5 to 10 2 to 3 1 3 to 5 ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If the length of overland flow from the critical point to the mouth of drain is 13.58 km and difference in level between the critical point and drain mouth is 10 m, the inlet time is 4 hours 8 hours 2 hours 6 hours 4 hours 8 hours 2 hours 6 hours ANSWER DOWNLOAD EXAMIANS APP