GETCO Exam Paper (22-07-2015) The value of holding ratio of relay is always zero less than 1 greater than 1 Infinite zero less than 1 greater than 1 Infinite ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which power plant may take several days to start up and shunt down? solar power plant Base load Peak load none of these solar power plant Base load Peak load none of these ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following is not function of substation batteries? emergency lighting circuits operating automatic control circuits operating protective relay systems provide supply to the excitation system emergency lighting circuits operating automatic control circuits operating protective relay systems provide supply to the excitation system ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) During the insulation co-ordination in the sub station, the lowest insulation strength is at bus bar transformer CTs and PTs circuit breaker bus bar transformer CTs and PTs circuit breaker ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following is the wrong statement in terms of slack bus? it should be located at the centre of the area it has finite reactive power generation capability it should be the largest generator bus in the system voltage and angle is specified at this bus it should be located at the centre of the area it has finite reactive power generation capability it should be the largest generator bus in the system voltage and angle is specified at this bus ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In a thermal power plant, heat from the flue gases is recovered in condenser chimney Economizer Electric precipitator condenser chimney Economizer Electric precipitator ANSWER DOWNLOAD EXAMIANS APP