GETCO Exam Paper (22-07-2015) Earth wire on EHV overhead transmission line is provided to protect the line against excessive fault voltages corona effect switching surge lightning surge excessive fault voltages corona effect switching surge lightning surge ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In G-S method of power flow problem, the number of iterations _____ depends on tolerance depends on no of buses depends on voltage control buses remains fixed depends on tolerance depends on no of buses depends on voltage control buses remains fixed ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) What is the surge impedance loading of 400 kV line with surge impedance given as 160 Ω 400 MW 1000 MW 250 MW 1000 kW 400 MW 1000 MW 250 MW 1000 kW ANSWER EXPLANATION DOWNLOAD EXAMIANS APP SIL = (kV)²/Z₀
GETCO Exam Paper (22-07-2015) The recent (as on 22/07/2015) Mahakumbh is held at Haridwar Nasik Alahabad Ujjain Haridwar Nasik Alahabad Ujjain ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Which of the following is the wrong statement in terms of slack bus? it should be located at the centre of the area it should be the largest generator bus in the system it has finite reactive power generation capability voltage and angle is specified at this bus it should be located at the centre of the area it should be the largest generator bus in the system it has finite reactive power generation capability voltage and angle is specified at this bus ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) For given kVAR and line voltage the ratio of star to delta value of capacitor is 0.33333333333333 1 3 1.73 0.33333333333333 1 3 1.73 ANSWER DOWNLOAD EXAMIANS APP