Industrial Engineering and Production Management The technique for establishing and maintaining priorities among the various jobs of any project is known as Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique Short interval scheduling Critical ratio scheduling Slotting technique for scheduling Event flow scheduling technique Short interval scheduling ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main disadvantage of line organisation is Communication delays occur Top level executives have to do excessive work All of these Structure is rigid Communication delays occur Top level executives have to do excessive work All of these Structure is rigid ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Linear programming can be applied successfully to Banks Chemical industry Oil industry All of these Banks Chemical industry Oil industry All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Total float Interfering float Duration Free float Total float Interfering float Duration ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Early finish Late finish Late start Early start Early finish Late finish Late start Early start ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time taken by a trained worker to perform an operation, while working a steady pace, is known as Normal time Standard time None of the listed here Representative time Normal time Standard time None of the listed here Representative time ANSWER DOWNLOAD EXAMIANS APP