Industrial Engineering and Production Management The technique for establishing and maintaining priorities among the various jobs of any project is known as Slotting technique for scheduling Short interval scheduling Event flow scheduling technique Critical ratio scheduling Slotting technique for scheduling Short interval scheduling Event flow scheduling technique Critical ratio scheduling ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The simplex method is the basic method for Model analysis Value analysis Operation research Linear programming Model analysis Value analysis Operation research Linear programming ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed All of these The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed All of these The activity is critical and any delay in its performance will delay the completion of whole project ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Routing prescribes the Inspection of final product Flow of material in the plant Proper utilization of machines Proper utilization of man power Inspection of final product Flow of material in the plant Proper utilization of machines Proper utilization of man power ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum) There is no such criterion CAM < DAM CAM > DAM CAM = DAM There is no such criterion CAM < DAM CAM > DAM CAM = DAM ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management PERT is the Activity oriented technique Target oriented technique Time oriented technique Event oriented technique Activity oriented technique Target oriented technique Time oriented technique Event oriented technique ANSWER DOWNLOAD EXAMIANS APP