Power Systems The steam power plant efficiency can be improved by using large quantity of water. decreasing the load on the plant. using high temperature and high pressure steam. burning large amount of coal. using large quantity of water. decreasing the load on the plant. using high temperature and high pressure steam. burning large amount of coal. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Find the value of a729, where "a" is the operator 0 α² α 1 0 α² α 1 ANSWER DOWNLOAD EXAMIANS APP
Power Systems The rating of CB is in terms of voltage. volt - ampere. current. VAR. voltage. volt - ampere. current. VAR. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Find the number of strands of ACSR conductor for 3 layer transmission line? 1 7 19 29 1 7 19 29 ANSWER DOWNLOAD EXAMIANS APP
Power Systems The positive, negative and zero sequence impedances of a transmission line are 0.5,0.5 and 1.1 pu respectively. The self (Zs) and mutual (Zm) impedances of the line will be given by Zs = 0.5 pu, Zm =0.6 pu Zs = 0.6 pu, Zm =0.5 pu Zs = 0.2 pu, Zm =0.7 pu Zs = 0.7 pu, Zm =0.2 pu Zs = 0.5 pu, Zm =0.6 pu Zs = 0.6 pu, Zm =0.5 pu Zs = 0.2 pu, Zm =0.7 pu Zs = 0.7 pu, Zm =0.2 pu ANSWER DOWNLOAD EXAMIANS APP
Power Systems A thermal power plant is being supplied with coal having much more ash content than that for which it was designed. Which of its following units needs major modifications Cooling tower. Ash handling unit. Condenser. Pulversing unit. Cooling tower. Ash handling unit. Condenser. Pulversing unit. ANSWER DOWNLOAD EXAMIANS APP