Power Systems The power output from an hydroelectric plants depend on type of turbine, type of dam and type of catchment area. discharge, system efficiency. type of dam, type of catchment area and discharge. type of dam, head, system efficiency. type of turbine, type of dam and type of catchment area. discharge, system efficiency. type of dam, type of catchment area and discharge. type of dam, head, system efficiency. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Pumped storage plant is a peak load plant both 1 and 2 base load plant None of these peak load plant both 1 and 2 base load plant None of these ANSWER DOWNLOAD EXAMIANS APP
Power Systems The water from a catchment is 60*106 cu m annually and hydro station has head of 40 m. Assuming ideal generator and turbine, the power that can be theoretically generated is 500 kW 750 kW 300 kW 250 kW 500 kW 750 kW 300 kW 250 kW ANSWER DOWNLOAD EXAMIANS APP
Power Systems The time taken by the turbine to fall to 0 rpm speed from 3000 rpm is called settling time. damping time. coasting time. stopping time. settling time. damping time. coasting time. stopping time. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A gas turbine power plant is best suited for Base load. Emergency. None of these. Peak load. Base load. Emergency. None of these. Peak load. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Units of incremental cost is RsMW/hr MWhr/Rs Rs/MWhr Rs/hr RsMW/hr MWhr/Rs Rs/MWhr Rs/hr ANSWER DOWNLOAD EXAMIANS APP