Building Construction The form Work including the props can be removed from beams, only after 14 days 7 days 3 days 21 days 14 days 7 days 3 days 21 days ANSWER DOWNLOAD EXAMIANS APP
Building Construction In case of foundations on sandy soil, maximum permissible differential settlement, is usually limited to 45 mm 35 mm 25 mm 15 mm 45 mm 35 mm 25 mm 15 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Crown is located at None of these Highest point on the extrados of the arch Highest point on the intrados of the arch Skew-back of the arch None of these Highest point on the extrados of the arch Highest point on the intrados of the arch Skew-back of the arch ANSWER DOWNLOAD EXAMIANS APP
Building Construction The vertical sides of a door and window openings provided in a wall, are known as None of these Reveals Verticals Jambs None of these Reveals Verticals Jambs ANSWER DOWNLOAD EXAMIANS APP
Building Construction During percussion drilling Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole The soil to a considerable depth below the bottom of the hole gets disturbed All listed here Caving or mixing of strata are caused in soft soils or cohesion-less soils Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole The soil to a considerable depth below the bottom of the hole gets disturbed All listed here Caving or mixing of strata are caused in soft soils or cohesion-less soils ANSWER DOWNLOAD EXAMIANS APP
Building Construction In grillage foundations, distance between flanges of grillage beams, is kept 40 cm Equal to flange width Twice the flange width Maximum of (A), (B) and (C) 40 cm Equal to flange width Twice the flange width Maximum of (A), (B) and (C) ANSWER DOWNLOAD EXAMIANS APP