Waste Water Engineering The factor responsible for purification of sewage in river is Temperature Hydrology All listed here Dissolved oxygen in water Temperature Hydrology All listed here Dissolved oxygen in water ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Which one of the following tests is used for testing sewer pipes? Mirror test Water test All of these Ball test Mirror test Water test All of these Ball test ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Discrete or granular particles change their Weight Shape None of these Size Weight Shape None of these Size ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The dimensions of a rectangular settling tank are: length 24 m, width 6 m and depth 3 m. If 2 hour detention period for tanks is recommended, the rate of flow of sewage per hour, is 204 cu.m 208 cu.m 212 cu.m 216 cu.m 204 cu.m 208 cu.m 212 cu.m 216 cu.m ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The disintegrating pump in which solid matter is broken up before passing out, is None of these Pneumatic ejector Reciprocating pump Centrifugal pump None of these Pneumatic ejector Reciprocating pump Centrifugal pump ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The intensity of rain is expressed in cm/day cm/hour cm/minute None of these cm/day cm/hour cm/minute None of these ANSWER DOWNLOAD EXAMIANS APP