Building Construction The differential settlement in case of foundations on sandy soils should not exceed 25 mm 65 mm 100 mm 40 mm 25 mm 65 mm 100 mm 40 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The compaction of concrete in the drilled pile hole is done by compressed air in the case of Pressure pile Franki pile Simplex pile Vibro pile Pressure pile Franki pile Simplex pile Vibro pile ANSWER DOWNLOAD EXAMIANS APP
Building Construction A wall constructed to resist the pressure of an earth filling, is called Parapet wall Buttress Retaining wall Breast wall Parapet wall Buttress Retaining wall Breast wall ANSWER DOWNLOAD EXAMIANS APP
Building Construction The type of joint commonly used at the junction of a principal rafter and tie beam in timber trusses is Butt joint Mortise and tenon joint Mitred joint Oblique mortise and tenon joint Butt joint Mortise and tenon joint Mitred joint Oblique mortise and tenon joint ANSWER DOWNLOAD EXAMIANS APP
Building Construction For a wall carrying heavy load on low bearing capacity soil, Lean concrete bed is provided Thick concrete bed is provided Reinforced concrete bed is provided Both (A) and (C) of the above Lean concrete bed is provided Thick concrete bed is provided Reinforced concrete bed is provided Both (A) and (C) of the above ANSWER DOWNLOAD EXAMIANS APP
Building Construction For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is 3, 2, 5, 1, 4 1, 2, 3, 4, 5 2, 1, 3, 5, 4 5, 4, 3, 2, 1 3, 2, 5, 1, 4 1, 2, 3, 4, 5 2, 1, 3, 5, 4 5, 4, 3, 2, 1 ANSWER DOWNLOAD EXAMIANS APP