The differential settlement in case of foundations on sandy soils should not exceed

100 mm
40 mm
25 mm
65 mm

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The pile provided with one or more bulles in its vertical shaft, is generally known as

Under-ream pile
Friction pile
Sheet pile
Bearing pile

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
An arch may fail due to

All listed here
Crushing of the material
Uneven settlement of abutments
Sliding of voussoirs

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The form Work including the props can be removed from beams, only after

7 days
14 days
21 days
3 days

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The members which support covering material of a sloping roof, are

Rafters
Struts
Battens
Purlins

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
In which of the following pairs both trees yield soft wood?

Deodar and Shishum
Chir and sal
Chir and deodar
Sal and teak

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Building Construction

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑