Building Construction The Auger boring method is not suitable for Cemented soil Very hard soil Vary soft soil All of these Cemented soil Very hard soil Vary soft soil All of these ANSWER DOWNLOAD EXAMIANS APP
Building Construction The additional piles which are driven to increase the capacity of supporting loads on vertical piles, are known Construction piles Raking piles Sinking piles Eccentric piles Construction piles Raking piles Sinking piles Eccentric piles ANSWER DOWNLOAD EXAMIANS APP
Building Construction The nominal thickness of an expansion joint in brick walls, is kept more than 5 mm 10 mm 20 mm 15 mm 5 mm 10 mm 20 mm 15 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction A temporary rigid structure having platforms to enable masons to work at different stages of a building, is known as Under pinning Scaffolding Dead shore Raking shore Under pinning Scaffolding Dead shore Raking shore ANSWER DOWNLOAD EXAMIANS APP
Building Construction If a is the offset of concrete bed in cms, and d is the depth of concrete bed in cms, then d = 0.775 a d = 0.445 a None of these d = 0.557 a d = 0.775 a d = 0.445 a None of these d = 0.557 a ANSWER DOWNLOAD EXAMIANS APP
Building Construction During percussion drilling The soil to a considerable depth below the bottom of the hole gets disturbed Caving or mixing of strata are caused in soft soils or cohesion-less soils Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole All listed here The soil to a considerable depth below the bottom of the hole gets disturbed Caving or mixing of strata are caused in soft soils or cohesion-less soils Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole All listed here ANSWER DOWNLOAD EXAMIANS APP