Building Construction

Building Construction
The depth of excavation of foundations, is generally measured with a

Steel tape
Boning rod
Levelling staff
Ranging rod

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The triangular space formed between the extrados and the horizontal line drawn through the crown of an arch is known as

Spandril
Voussoirs
Haunch
Skewbacks

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The type of pointing in which upper side of mortar joints is kept about 12 mm inside the face of the masonry and bottom is kept flushed with face of wall, is

Grooved pointing
Recessed pointing
Truck pointing
Struck pointing

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The angle between skew back of a flat arch and the horizontal, is kept approximately equal to

0°
30°
90°
60°

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
A pre-stressed concrete pile is

All of these
Extremely durable
Lighter in weight
Easy to handle

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
The form work from the sides of beams can be removed only after

4 days
1 day
14 days
7 days

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Building Construction

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑