MGVCL Exam Paper (30-07-2021 Shift 1)
Simultaneous tripping of the circuit breaker at both ends of a transmission line is achieved by

none of these
pilot protection
overcurrent protection
distance protection

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Murray loop test is performed on a faulty cable 300 m long. At balance, the resistance connected to the faulty core was set at 15 Ω and the resistance of the resistor connected to the sound core was 45 Ω. Calculate the distance of the fault point from the test end.

75 m
150 m
225 m
450 m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
___ is the short time reduction in the rms voltage between 0.1 to 0.9 p.u for a duration of ___

Voltage sag, 0.5 cycle to 1 minute.
Voltage swell, greater than 1 minute
Voltage swell, 0.5 cycle to 1 minute.
Voltage sag, greater than 1 minute

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Determine the ohmic value of the current limiting reactor per phase external to a 30 MVA, 11 kV, 50 Hz, three phase synchronous generator which can limit the current on short circuit of 5 times the full load current. The reactance of the synchronous generator is 0.05 pu.

0.405 Ω
0.805 Ω
0.305 Ω
0.605 Ω

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP