MGVCL Exam Paper (30-07-2021 Shift 1)
Simultaneous tripping of the circuit breaker at both ends of a transmission line is achieved by

none of these
distance protection
pilot protection
overcurrent protection

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Case 1: The PV connected to the DC bus was injecting 20 kW of power constituting of 1 kW of loss
Case 2: The same PV is connected to the AC bus constituting to 1.5 kW loss. Find out the change in efficiency from Case 1 to Case 2?

2.5% decrease
2.5% increase
5% decrease
5% increase

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
A balanced delta connected load of 8+j6 Ω per phase is connected to a 415 V, 50 Hz, 3-phase supply lines. If the input power factor is improved to 0.9 by connecting a star connected capacitor bank, then the required kVAR of the bank is

14.98 kVAR
8.98 kVAR
10.98 kVAR
16.98 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP