Industrial Engineering and Production Management In A-B-C analysis, which class of items are generally large in number? B C None of these A B C None of these A ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which one of the following chart gives simultaneously information about the progress of work and machine loading? Gantt chart Man-machine chart Process chart Machine load chart Gantt chart Man-machine chart Process chart Machine load chart ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The important file in making a PERT is All of the these An event can't be accomplished until activities leading to it are completed No activity from any event can be started from preceding event till it is completed Length of arrow has nothing to do with time All of the these An event can't be accomplished until activities leading to it are completed No activity from any event can be started from preceding event till it is completed Length of arrow has nothing to do with time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following layouts is suited for mass production? Fixed position layout Plant layout Process layout Product layout Fixed position layout Plant layout Process layout Product layout ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A dummy activity in a net work diagram All of these Does not consume time or resources Is represented by a dotted line Is an artificial activity All of these Does not consume time or resources Is represented by a dotted line Is an artificial activity ANSWER DOWNLOAD EXAMIANS APP