Which of the following are the guidelines for the construction of a network diagram?

All of the these
Dummy activity consumes no time or resource
Each activity is represented by one and only one arrow in the network
Dangling must be avoided in a network diagram

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Which of the following statement is correct about the network diagram?

The head of the arrow represents the end of an activity.
The events are represented graphically by circles or nodes at the beginning and the end of activity by arrows.
All of the these
The tail end of the arrow represents the start of an activity.

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Pick up the incorrect statement about advantages of work sampling

No time measuring devices are generally needed
Simultaneous study of many operators may be made by a single observer
Calculations are easier, method is economical and less time consuming
Permits a fine breakdown of activities and delays

ANSWER DOWNLOAD EXAMIANS APP