Industrial Engineering and Production Management Pick up the incorrect statement about advantages of work sampling No time measuring devices are generally needed Calculations are easier, method is economical and less time consuming Permits a fine breakdown of activities and delays Simultaneous study of many operators may be made by a single observer No time measuring devices are generally needed Calculations are easier, method is economical and less time consuming Permits a fine breakdown of activities and delays Simultaneous study of many operators may be made by a single observer ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Break-even analysis shows profit when Sales revenue < total cost Variable cost < fixed cost Sales revenue = total cost Sales revenue > total cost Sales revenue < total cost Variable cost < fixed cost Sales revenue = total cost Sales revenue > total cost ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Merit Rating is the method of determining worth of An individual employee A job Machine A particular division in workshop An individual employee A job Machine A particular division in workshop ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive Any one of the above The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed Any one of the above The activity is critical and any delay in its performance will delay the completion of whole project It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Halsey plan of wage incentive Does not guarantee minimum wage Is applied to all level of workers Is not applied to all level of workers Is based upon efficiency of worker Does not guarantee minimum wage Is applied to all level of workers Is not applied to all level of workers Is based upon efficiency of worker ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good LF = LS + D LS = LFD EF = ES + D All of these LF = LS + D LS = LFD EF = ES + D All of these ANSWER DOWNLOAD EXAMIANS APP