Industrial Engineering and Production Management The essential condition for the decompression of an activity is that An activity could be decompressed to the maximum extent of its normal time An activity could be decompressed to the maximum extent of its normal time After decompression the time of an activity invariably exceeds its normal time The project time should change due to decompression An activity could be decompressed to the maximum extent of its normal time An activity could be decompressed to the maximum extent of its normal time After decompression the time of an activity invariably exceeds its normal time The project time should change due to decompression ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to MAPI formula, the old machine should be replaced by new one when (Here, CAM = Challenger's Adverse minimum, DAM = Defender's Adverse minimum) CAM < DAM CAM = DAM CAM > DAM There is no such criterion CAM < DAM CAM = DAM CAM > DAM There is no such criterion ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Bar charts are suitable for All of these Large projects Minor works Major works All of these Large projects Minor works Major works ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The simplex method is the basic method for Linear programming Model analysis Value analysis Operation research Linear programming Model analysis Value analysis Operation research ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management 'O' on a PERT/CPM chart represents An event to be transferred to other network chart A significant event representing some milestone An ordinary event Dangling event An event to be transferred to other network chart A significant event representing some milestone An ordinary event Dangling event ANSWER DOWNLOAD EXAMIANS APP