GETCO Exam Paper (22-07-2015) The constraints that are to be met with while solving UC problem are Minimum down time Minimum up time all are correct Spinning reserve Minimum down time Minimum up time all are correct Spinning reserve ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) 100% string efficiency means Zero potential across each disc Equal potential across each disc One of the insulator discs shorted None uniform potential distribution across each disc Zero potential across each disc Equal potential across each disc One of the insulator discs shorted None uniform potential distribution across each disc ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Critical clearing time of a fault in a power system is related to Short circuit limit Transient stability limit Reactive power limit Steady state limit Short circuit limit Transient stability limit Reactive power limit Steady state limit ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Fast excitation system of the generator will _____ Improve the dynamic stability Improve the power factor Improve the reactive power control Improve the voltage control Improve the dynamic stability Improve the power factor Improve the reactive power control Improve the voltage control ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The Z matrix of 2 port network is given by [0.9 0.2 : 0.2 0.6]. The element Y22 of the corresponding Y matrix of the same network is given by 0.4 1.2 -0.4 1.8 0.4 1.2 -0.4 1.8 ANSWER DOWNLOAD EXAMIANS APP