GETCO Exam Paper (22-07-2015)

GETCO Exam Paper (22-07-2015)
Power Factor correcting element is generally connected in _____

series with source
parallel to the load
parallel to source
series with load

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
The national song of India was composed by

Jai Shankar Prasad
Bankim Chandra Chatterji
Iqbal
Rabindranath Tagore

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Fast excitation system of the generator will _____

Improve the voltage control
Improve the reactive power control
Improve the dynamic stability
Improve the power factor

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
An over-current relay of current rating 5 A and setting 150% is connected to a 200/5 A CT. Then the relay to pickup, the line current required is

150
300
200
100

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Which of the following is not function of substation batteries?

provide supply to the excitation system
emergency lighting circuits
operating protective relay systems
operating automatic control circuits

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
The breaking capacity of a CB is usually expressed interms of

volts
MVA
amperes
MW

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON GETCO Exam Paper (22-07-2015)

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑