Industrial Engineering and Production Management Positive slack on a PERT indicates that project is Beyond schedule Ahead of schedule On critical path As per schedule Beyond schedule Ahead of schedule On critical path As per schedule ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Bar chart is suitable for All of these Major work Minor work Large project All of these Major work Minor work Large project ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time taken by a trained worker to perform an operation, while working a steady pace, is known as Normal time Standard time Representative time None of the listed here Normal time Standard time Representative time None of the listed here ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be TR + (S - T) × R TR + [(S - T)/S] × R TR + [(S - T)/2] × R TR TR + (S - T) × R TR + [(S - T)/S] × R TR + [(S - T)/2] × R TR ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A milestone chart Points outgoing ahead of schedule of jobs, if any None of the these Shows the inter dependences of various jobs Depicts the delay of jobs, if any Points outgoing ahead of schedule of jobs, if any None of the these Shows the inter dependences of various jobs Depicts the delay of jobs, if any ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to All of these Latest finish time earliest finish time (EFT) Latest start time earliest start time TLEFT All of these Latest finish time earliest finish time (EFT) Latest start time earliest start time TLEFT ANSWER DOWNLOAD EXAMIANS APP