Industrial Engineering and Production Management Micro-motion study involves following number of fundamental hand motions 12 16 20 8 12 16 20 8 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The technique of value analysis can be applied to Any item Crash programmer items only Simple items only Complicated items only Any item Crash programmer items only Simple items only Complicated items only ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Slack of various events on the critical path in PERT/CPM chart Decreases continuously May increase or decrease depending on various factors Increases continuously Remain constant Decreases continuously May increase or decrease depending on various factors Increases continuously Remain constant ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The basic difference between PERT and CPM is that Critical path is determined in PERT only PERT deals with events and CPM with activities Costs are considered on CPM only and not in PERT Guessed times are used in PERT and evaluated times in CPM Critical path is determined in PERT only PERT deals with events and CPM with activities Costs are considered on CPM only and not in PERT Guessed times are used in PERT and evaluated times in CPM ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to Rowan plan of wage incentive system, bonus is paid to a worker On the percentage of time worked Whose output exceeds 67% efficiency On the percentage of time saved On the percentage of standard time On the percentage of time worked Whose output exceeds 67% efficiency On the percentage of time saved On the percentage of standard time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management An activity of the project is graphically represented by ________ on the network diagram. A circle None of these A straight line An arrow A circle None of these A straight line An arrow ANSWER DOWNLOAD EXAMIANS APP