Pick up the correct step used for scheduling a project by C.P.M.

Sequence of various activities is made according to their importance
Required time for each activity is established
A project is divided into various activities
All of these

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
When slack of an activity is negative

The activity is critical and any delay in its performance will delay the completion of whole project
It represents a situation where extra resources are available and the completion of project is not delayed
It represents that a programme falls behind schedule and additional resources are required to complete the project in time
All of these

ANSWER DOWNLOAD EXAMIANS APP