Process Equipment and Plant Design Oxygen carrying pipelines in chemical industries are coloured with __________ colour. Blue Red Black Yellow Blue Red Black Yellow ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In a distillation column, minimum clearance to be maintained betweeen the overflow weir and the last row of the bubble caps is __________ cms. 7.5 20 2.5 15 7.5 20 2.5 15 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design For storing hazardous chemicals in large storage tanks, the minimum safe distance between the two tanks should range between __________ times the tank diameter. 1 to 1.5 4 to 5 2.5 to 3.5 6 to 8 1 to 1.5 4 to 5 2.5 to 3.5 6 to 8 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Needle valves are generally not used for Very accurate flow control Very large diameter pipes Smaller sizes of pipe High pressure throttling service Very accurate flow control Very large diameter pipes Smaller sizes of pipe High pressure throttling service ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In a rotary drier, the average retention time of solid is(where Z = length of the drier, metres ρ = apparent solid density, kg/m³ L = flow rate of dry solids, kg/see. m² drier cross-section H = hold up of solid.) Z.H.ρ/L L/Z.H.ρ H.ρ/L Z.H/L.ρ Z.H.ρ/L L/Z.H.ρ H.ρ/L Z.H/L.ρ ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In case of 1.5" heat exchanger tubes, the inside flow area __________ with decrease in BWG. Increases Decreases None of these Remains same Increases Decreases None of these Remains same ANSWER DOWNLOAD EXAMIANS APP