Insulation Power Factor testing on an oil-filled transformer is not helpful in determining ___

Movement of the windings (change in capacitance)
Condition of paper insulation (change in watts losses)
Whether the oil test indicates moisture
Turns ratio values

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
In a 3-phase, 4-wire, 400/230 V system, a lamp (L1) of 100 W is connected to one phase and neutral and a lamp (L2) of 150 W is connected to the second pahse and neutral. If the neutral wire is disconnected accidently, what will be the voltage across a 100 W lamp (L1)?

180V
120V
160 V
240V

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
What is the largest thermal power plant in India?

Vindhyachal Thermal Power Station
Talcher Super Thermal Power Station
Sasan Ultra Mega Power Plant
Mundra Thermal Power Station

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Determine maximum permissible load which a 15 MVA, ONAN cooled transformer to IS : 2026 can take for 6 hr, if the initial load on it was 12 MVA. The weighted ambient temperature is 20˚C. Assume the permissible load kVA as a fraction of rated kVA is 1.25.

9.6 MVA
18.75 MVA
12 MVA
15 MVA