Industrial Engineering and Production Management The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time) (to + tp + 4tn)/6 (to + tp + tn)/3 (to + 2tp + tn)/4 (to + 4tp + tn)/5 (to + tp + 4tn)/6 (to + tp + tn)/3 (to + 2tp + tn)/4 (to + 4tp + tn)/5 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Acceptance sampling is used in Mass production Job production All of these Batch production Mass production Job production All of these Batch production ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is Cost of project will always be more than the estimated cost, if no timely corrections are taken Activities are fixed and can't be changed A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities Cost of project will always be more than the estimated cost, if no timely corrections are taken Activities are fixed and can't be changed A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Bin card is used in Foundry shop Administrative wing Stores Workshop Foundry shop Administrative wing Stores Workshop ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The performance of a specific task in CPM is known as Contract Activity Event Dummy Contract Activity Event Dummy ANSWER DOWNLOAD EXAMIANS APP