Industrial Engineering and Production Management Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it Consumes time, but no resources Consumes neither time nor resources Is a dangling event Consumes resources but no time Consumes time, but no resources Consumes neither time nor resources Is a dangling event Consumes resources but no time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management M.T.M. is used to Improve existing methods Develop effective methods in advance of the beginning of production Establish time standards All of these Improve existing methods Develop effective methods in advance of the beginning of production Establish time standards All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if All variables and constants are known and form a linear equation Complete details of items in, waiting line are known The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Arrival and waiting times are known and can be grouped to form a waiting line model All variables and constants are known and form a linear equation Complete details of items in, waiting line are known The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Arrival and waiting times are known and can be grouped to form a waiting line model ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to Formulate a proper incentive scheme Plan and schedule of production Estimate the selling prices and delivery dates All of these Formulate a proper incentive scheme Plan and schedule of production Estimate the selling prices and delivery dates All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following equations is not in conformity with others? Organization performance × motivation = profits Attitude × situation = motivation Ability × motivation = performance Knowledge × skill = ability Organization performance × motivation = profits Attitude × situation = motivation Ability × motivation = performance Knowledge × skill = ability ANSWER DOWNLOAD EXAMIANS APP