Industrial Engineering and Production Management Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it Consumes time, but no resources Consumes neither time nor resources Is a dangling event Consumes resources but no time Consumes time, but no resources Consumes neither time nor resources Is a dangling event Consumes resources but no time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management M.T.M. is used to Establish time standards Develop effective methods in advance of the beginning of production Improve existing methods All of these Establish time standards Develop effective methods in advance of the beginning of production Improve existing methods All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if Arrival and waiting times are known and can be grouped to form a waiting line model Complete details of items in, waiting line are known All variables and constants are known and form a linear equation The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Arrival and waiting times are known and can be grouped to form a waiting line model Complete details of items in, waiting line are known All variables and constants are known and form a linear equation The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to Formulate a proper incentive scheme All of these Estimate the selling prices and delivery dates Plan and schedule of production Formulate a proper incentive scheme All of these Estimate the selling prices and delivery dates Plan and schedule of production ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following equations is not in conformity with others? Attitude × situation = motivation Organization performance × motivation = profits Ability × motivation = performance Knowledge × skill = ability Attitude × situation = motivation Organization performance × motivation = profits Ability × motivation = performance Knowledge × skill = ability ANSWER DOWNLOAD EXAMIANS APP