Industrial Engineering and Production Management Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it Consumes time, but no resources Consumes neither time nor resources Consumes resources but no time Is a dangling event Consumes time, but no resources Consumes neither time nor resources Consumes resources but no time Is a dangling event ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management M.T.M. is used to Develop effective methods in advance of the beginning of production Improve existing methods Establish time standards All of these Develop effective methods in advance of the beginning of production Improve existing methods Establish time standards All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if Complete details of items in, waiting line are known The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known All variables and constants are known and form a linear equation Arrival and waiting times are known and can be grouped to form a waiting line model Complete details of items in, waiting line are known The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known All variables and constants are known and form a linear equation Arrival and waiting times are known and can be grouped to form a waiting line model ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to Plan and schedule of production Estimate the selling prices and delivery dates Formulate a proper incentive scheme All of these Plan and schedule of production Estimate the selling prices and delivery dates Formulate a proper incentive scheme All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following equations is not in conformity with others? Ability × motivation = performance Knowledge × skill = ability Attitude × situation = motivation Organization performance × motivation = profits Ability × motivation = performance Knowledge × skill = ability Attitude × situation = motivation Organization performance × motivation = profits ANSWER DOWNLOAD EXAMIANS APP