Industrial Engineering and Production Management Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it Is a dangling event Consumes resources but no time Consumes neither time nor resources Consumes time, but no resources Is a dangling event Consumes resources but no time Consumes neither time nor resources Consumes time, but no resources ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management M.T.M. is used to All of these Establish time standards Improve existing methods Develop effective methods in advance of the beginning of production All of these Establish time standards Improve existing methods Develop effective methods in advance of the beginning of production ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if All variables and constants are known and form a linear equation Arrival and waiting times are known and can be grouped to form a waiting line model The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Complete details of items in, waiting line are known All variables and constants are known and form a linear equation Arrival and waiting times are known and can be grouped to form a waiting line model The laws governing arrivals, service times, and the order in which the arriving units are taken into source are known Complete details of items in, waiting line are known ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to Estimate the selling prices and delivery dates Plan and schedule of production Formulate a proper incentive scheme All of these Estimate the selling prices and delivery dates Plan and schedule of production Formulate a proper incentive scheme All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following equations is not in conformity with others? Attitude × situation = motivation Organization performance × motivation = profits Knowledge × skill = ability Ability × motivation = performance Attitude × situation = motivation Organization performance × motivation = profits Knowledge × skill = ability Ability × motivation = performance ANSWER DOWNLOAD EXAMIANS APP