Industrial Engineering and Production Management The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time) (to + tp + tn)/3 (to + 2tp + tn)/4 (to + tp + 4tn)/6 (to + 4tp + tn)/5 (to + tp + tn)/3 (to + 2tp + tn)/4 (to + tp + 4tn)/6 (to + 4tp + tn)/5 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management For a product layout the material handling equipment must Be designed as special purpose for a particular application Have full flexibility Be a general purpose type Employ conveyor belts, trucks, tractors etc. Be designed as special purpose for a particular application Have full flexibility Be a general purpose type Employ conveyor belts, trucks, tractors etc. ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management According to Rowan plan of wage incentive system, bonus is paid to a worker On the percentage of standard time On the percentage of time worked Whose output exceeds 67% efficiency On the percentage of time saved On the percentage of standard time On the percentage of time worked Whose output exceeds 67% efficiency On the percentage of time saved ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed All of these It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed All of these It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Positive slack on a PERT indicates that project is Ahead of schedule As per schedule On critical path Beyond schedule Ahead of schedule As per schedule On critical path Beyond schedule ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pick up the incorrect statement about advantages of work sampling Permits a fine breakdown of activities and delays Simultaneous study of many operators may be made by a single observer Calculations are easier, method is economical and less time consuming No time measuring devices are generally needed Permits a fine breakdown of activities and delays Simultaneous study of many operators may be made by a single observer Calculations are easier, method is economical and less time consuming No time measuring devices are generally needed ANSWER DOWNLOAD EXAMIANS APP