Industrial Engineering and Production Management The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time) (to + 4tp + tn)/5 (to + 2tp + tn)/4 (to + tp + 4tn)/6 (to + tp + tn)/3 (to + 4tp + tn)/5 (to + 2tp + tn)/4 (to + tp + 4tn)/6 (to + tp + tn)/3 ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed All of these It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project It represents a situation where extra resources are available and the completion of project is not delayed All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The most suitable incentive plan for the maintenance section of an industry will be Group incentive plan Simplification Profit sharing plans Piece rate system Group incentive plan Simplification Profit sharing plans Piece rate system ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The essential condition for the decompression of an activity is that An activity could be decompressed to the maximum extent of its normal time An activity could be decompressed to the maximum extent of its normal time After decompression the time of an activity invariably exceeds its normal time The project time should change due to decompression An activity could be decompressed to the maximum extent of its normal time An activity could be decompressed to the maximum extent of its normal time After decompression the time of an activity invariably exceeds its normal time The project time should change due to decompression ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A device used for lifting or lowering objects suspended from a hook at the end of retractable chains or cable is called Hoist Jib crane Chain conveyor Portable elevator Hoist Jib crane Chain conveyor Portable elevator ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Positive slack on a PERT indicates that project is As per schedule On critical path Ahead of schedule Beyond schedule As per schedule On critical path Ahead of schedule Beyond schedule ANSWER DOWNLOAD EXAMIANS APP