Industrial Engineering and Production Management The bonus increases in proportion to the increase in efficiency. This statement applies to Rowan plan Halsey plan Gantt plan Emerson's efficiency plan Rowan plan Halsey plan Gantt plan Emerson's efficiency plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical path on PERT/CPM chart is obtained by joining the events having Average slack Minimum slack Maximum slack No slack Average slack Minimum slack Maximum slack No slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Duration Interfering float Free float Total float Duration Interfering float Free float ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The standard time for a job is Total work content + delay contingency allowance Total work content Base time + relaxation time Total work content + basic time Total work content + delay contingency allowance Total work content Base time + relaxation time Total work content + basic time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Time study is Time taken by workers to do a job The appraisal, in terms of time, of the value of work involving human effort Method of fixing time for workers Machine setting time Time taken by workers to do a job The appraisal, in terms of time, of the value of work involving human effort Method of fixing time for workers Machine setting time ANSWER DOWNLOAD EXAMIANS APP