Industrial Engineering and Production Management Critical path on PERT/CPM chart is obtained by joining the events having Maximum slack Minimum slack Average slack No slack Maximum slack Minimum slack Average slack No slack ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If (R) is the base rate guaranteed per hour, (S) is the standard time for the job and (T) is the actual time, then according to Rowan plan, wages for the job will be TR TR + (S - T) × R TR + [(S - T)/S] × R TR + [(S - T)/2] × R TR TR + (S - T) × R TR + [(S - T)/S] × R TR + [(S - T)/2] × R ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Works cost implies Factory expenses Primary cost + factory expenses Factory cost Primary cost Factory expenses Primary cost + factory expenses Factory cost Primary cost ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In value engineering, important consideration is given to Cost reduction Customer satisfaction Function concept Profit maximization Cost reduction Customer satisfaction Function concept Profit maximization ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Time study is used to Determine the number of machines a person may run Provide a basis for setting piece price or incentive wages All of the these Determine standard costs Determine the number of machines a person may run Provide a basis for setting piece price or incentive wages All of the these Determine standard costs ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Late start Early start Late finish Early finish Late start Early start Late finish Early finish ANSWER DOWNLOAD EXAMIANS APP