Industrial Engineering and Production Management
Activity slack or float of any event on a PERT/CPM chart is represented by

Latest start time of succeeding event earliest finish time of preceding event activity time
Latest start time of the event earliest start time of the event
Latest finish time of event earliest finish time of the event
Anyone of the above

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
Dispatching

Determines the programme for the operations
Is concerned with the starting of processes
Regulates the progress of job through various processes
Prescribes the sequence of operations to be followed

ANSWER DOWNLOAD EXAMIANS APP