Industrial Engineering and Production Management The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as Free float Total float Interfering float Duration Free float Total float Interfering float Duration ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Slack represents the difference between the Latest allowable time and the normal expected time Proposed allowable time and the earliest expected time Latest allowable time and the earliest expected time Normal allowable time and the latest expected time Latest allowable time and the normal expected time Proposed allowable time and the earliest expected time Latest allowable time and the earliest expected time Normal allowable time and the latest expected time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A feasible solution to the linear programming problem should Satisfy the non-negativity restrictions Optimise the objective function Satisfy the problem constraints Satisfy the problem constraints and non-negativity restrictions Satisfy the non-negativity restrictions Optimise the objective function Satisfy the problem constraints Satisfy the problem constraints and non-negativity restrictions ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Work study is mainly aimed at Developing the standard method and standard time of a job Economizing the motions involved on the part of the worker while performing a job Establishing the minimum time of completion of a job Determining the most efficient method of performing a job Developing the standard method and standard time of a job Economizing the motions involved on the part of the worker while performing a job Establishing the minimum time of completion of a job Determining the most efficient method of performing a job ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management If TL is the largest allowable event occurrence time, total activity slack (s) is equal to All of these TLEFT Latest finish time earliest finish time (EFT) Latest start time earliest start time All of these TLEFT Latest finish time earliest finish time (EFT) Latest start time earliest start time ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The standard time for a job is Total work content Base time + relaxation time Total work content + basic time Total work content + delay contingency allowance Total work content Base time + relaxation time Total work content + basic time Total work content + delay contingency allowance ANSWER DOWNLOAD EXAMIANS APP