RCC Structures Design In a singly reinforced beam, if the permissible stress in concrete reaches earlier than that in steel, the beam section is called Economic section Critical section Over reinforced section Under-reinforced section Economic section Critical section Over reinforced section Under-reinforced section ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design The advantage of a concrete pile over a timber pile, is No decay due to termites Higher bearing capacity All of these No restriction on length No decay due to termites Higher bearing capacity All of these No restriction on length ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design To ensure uniform pressure distribution, the thickness of the foundation, is Increased gradually towards the edge Kept uniform throughout Decreased gradually towards the edge Kept zero at the edge Increased gradually towards the edge Kept uniform throughout Decreased gradually towards the edge Kept zero at the edge ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design If the bearing capacity of soil is 10 tonnes/cm² and the projection of plain concrete footing from walls, is a cm, the depth D of footing is D = 0.775 √a D = 0.0775 a D = 0.775 a² D = 0.775 a D = 0.775 √a D = 0.0775 a D = 0.775 a² D = 0.775 a ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design Piles are usually driven by Drop hammer All listed here Diesel operated hammer Single acting steam hammer Drop hammer All listed here Diesel operated hammer Single acting steam hammer ANSWER DOWNLOAD EXAMIANS APP
RCC Structures Design In a simply supported slab, alternate bars are curtailed at 1/6th of the span 1/4th of the span 1/7th of the span 1/5th of the span 1/6th of the span 1/4th of the span 1/7th of the span 1/5th of the span ANSWER DOWNLOAD EXAMIANS APP