Waste Water Engineering If is the diameter of upper circular portion, the overall depth of New Egg shaped sewer section, is 1.425 D 1.350 D 1.250 D 1.625 D 1.425 D 1.350 D 1.250 D 1.625 D ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In detritus tanks, Organic and inorganic materials are separated Detention period is kept 3 to 4 minutes All listed here Flow velocity is kept 0.09 m/sec Organic and inorganic materials are separated Detention period is kept 3 to 4 minutes All listed here Flow velocity is kept 0.09 m/sec ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Ventilating shafts are provided to a sewer line at every 100 m 300 m 200 m 150 m 100 m 300 m 200 m 150 m ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The sewer which received discharge from two or more main sewers, is known as A main sewer A trunk sewer An intercepting sewer An outfall sewer A main sewer A trunk sewer An intercepting sewer An outfall sewer ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Removal of oil and grease from sewage, is known Screening Skimming None of these Filtration Screening Skimming None of these Filtration ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Large diameter sewers subjected to external pressure alone, are reinforced Near the inner surface of the pipe Near the outer surface of the pipe With elliptical cage Both A and B Near the inner surface of the pipe Near the outer surface of the pipe With elliptical cage Both A and B ANSWER DOWNLOAD EXAMIANS APP