Waste Water Engineering A circular sewer section is preferred to because All listed here It provides maximum hydraulic mean depth It is cheaper in construction It provides maximum area for a given perimeter All listed here It provides maximum hydraulic mean depth It is cheaper in construction It provides maximum area for a given perimeter ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The minimum diameter of a sewer is kept 20 cm 25 cm 10 cm 15 cm 20 cm 25 cm 10 cm 15 cm ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In a grit chamber of a sewage treatment plant, Depth of 0.9 m to 1.20 m is kept One minute of detention period is kept Flow velocity 0.15 m to 0.3 m/sec is kept All of these Depth of 0.9 m to 1.20 m is kept One minute of detention period is kept Flow velocity 0.15 m to 0.3 m/sec is kept All of these ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The factor responsible for purification of sewage in river is Dissolved oxygen in water All listed here Hydrology Temperature Dissolved oxygen in water All listed here Hydrology Temperature ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering It is customary to design a sewer for D.W.F. on the basis of Thrice the average demand Average demand Twice the average demand Four times the average demand Thrice the average demand Average demand Twice the average demand Four times the average demand ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The grit chambers of sewage treatment plants, are generally cleaned after 7 days 12 days 14 days 2 days 7 days 12 days 14 days 2 days ANSWER DOWNLOAD EXAMIANS APP