GETCO Exam Paper (22-07-2015) In G-S method of power flow problem, the number of iterations _____ depends on tolerance depends on voltage control buses remains fixed depends on no of buses depends on tolerance depends on voltage control buses remains fixed depends on no of buses ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In load flow analysis, the load at the bus is represented as none of these a voltag dependent impedance at the bus a constant current drawn from the bus a constant impedance connected at the bus none of these a voltag dependent impedance at the bus a constant current drawn from the bus a constant impedance connected at the bus ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The constraints that are to be met with while solving UC problem are Spinning reserve Minimum down time all are correct Minimum up time Spinning reserve Minimum down time all are correct Minimum up time ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) 100% string efficiency means One of the insulator discs shorted Equal potential across each disc Zero potential across each disc None uniform potential distribution across each disc One of the insulator discs shorted Equal potential across each disc Zero potential across each disc None uniform potential distribution across each disc ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Critical clearing time of a fault in a power system is related to Reactive power limit Steady state limit Short circuit limit Transient stability limit Reactive power limit Steady state limit Short circuit limit Transient stability limit ANSWER DOWNLOAD EXAMIANS APP