GETCO Exam Paper (22-07-2015) In G-S method of power flow problem, the number of iterations _____ remains fixed depends on no of buses depends on tolerance depends on voltage control buses remains fixed depends on no of buses depends on tolerance depends on voltage control buses ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In load flow analysis, the load at the bus is represented as a constant current drawn from the bus a voltag dependent impedance at the bus a constant impedance connected at the bus none of these a constant current drawn from the bus a voltag dependent impedance at the bus a constant impedance connected at the bus none of these ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) The constraints that are to be met with while solving UC problem are Minimum up time Spinning reserve Minimum down time all are correct Minimum up time Spinning reserve Minimum down time all are correct ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) 100% string efficiency means One of the insulator discs shorted Zero potential across each disc Equal potential across each disc None uniform potential distribution across each disc One of the insulator discs shorted Zero potential across each disc Equal potential across each disc None uniform potential distribution across each disc ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Critical clearing time of a fault in a power system is related to Short circuit limit Steady state limit Transient stability limit Reactive power limit Short circuit limit Steady state limit Transient stability limit Reactive power limit ANSWER DOWNLOAD EXAMIANS APP