GETCO Exam Paper (22-07-2015)
In G-S method of power flow problem, the number of iterations _____

depends on tolerance
depends on no of buses
remains fixed
depends on voltage control buses

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Which of the following is a reason to decouple AVR and LFC loops when there is a shortage of reactive power?

AVR loop response is slower than LFC loop
deference of error is the main reason
angle of the voltage is not considered
Change in voltage magnitude marginally affects real power

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
Which of the following is the wrong statement in terms of slack bus?

it should be located at the centre of the area
it should be the largest generator bus in the system
voltage and angle is specified at this bus
it has finite reactive power generation capability

ANSWER DOWNLOAD EXAMIANS APP