Building Construction
For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is

3, 2, 5, 1, 4
1, 2, 3, 4, 5
5, 4, 3, 2, 1
2, 1, 3, 5, 4

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Which one of the following activities is not correct as applicable to brick corbels

The maximum projection of the corbel should not be more than the thickness of the wall
The maximum projection of each corbel course should be limited to a quarter brick at a time
Stretcher bond is generally used for the construction of brick corbel
The discontinuous corbels are used to carry heavy concentrated loads

ANSWER DOWNLOAD EXAMIANS APP