Building Construction
For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is

2, 1, 3, 5, 4
3, 2, 5, 1, 4
5, 4, 3, 2, 1
1, 2, 3, 4, 5

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Assertion A : Shishum is used for decorative woodwork.Reason R : Shishum can be polished to an excellent finish.Select your answer according to the coding system given below:

Both A and R is true but R is not the correct explanation of A
A is true but R is false
A is false but R is true
Both A and R is true and R is the correct explanation of A

ANSWER DOWNLOAD EXAMIANS APP