Process Equipment and Plant Design Diameter of rivet hole (d, mm) and the plate thickness (t, mm) are related by Unwin's formula as D = 3√t D = 1.1 t D = 1.6 √t D = 1.5 t D = 3√t D = 1.1 t D = 1.6 √t D = 1.5 t ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In a multipass shell and tube heat exchanger, the problem of differential expansion between the shell and tube passes is taken care of by using a Floating head tube sheet U-bend Either A or B Neither A nor B Floating head tube sheet U-bend Either A or B Neither A nor B ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The retention time of material in a rotary dryer depends upon its Slope & length All of these Flights arrangement Rpm Slope & length All of these Flights arrangement Rpm ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Pick out the wrong statement pertaining to a shell and tube heat exchanger. The maximum unsupported tube span is generally about 75 times tube diameter, but is reduced to about 60 times for aluminium, copper & alloys of these Disk and doughnut baffle is the most commonly used baffle The minimum value of baffle spacing is 50 mm The maximum value of baffle spacing is equal to the I.D. of the shell The maximum unsupported tube span is generally about 75 times tube diameter, but is reduced to about 60 times for aluminium, copper & alloys of these Disk and doughnut baffle is the most commonly used baffle The minimum value of baffle spacing is 50 mm The maximum value of baffle spacing is equal to the I.D. of the shell ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Compensation against openings in process vessels for giving inlet and outlet connections, for providing sight glasses and manholes etc. is provided for strength and rigidity. The most efficient type of compensation is of __________ type. Nozzle or rim Flared out Ring plate Fluid in Nozzle or rim Flared out Ring plate Fluid in ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The absorption factor is defined as (where, S₁ = slope of the equilibrium curve, S₂ = slope of the operating line) S₁/S₂ S₁.S₂ 1/S₁.S₂ S₂/S₁ S₁/S₂ S₁.S₂ 1/S₁.S₂ S₂/S₁ ANSWER DOWNLOAD EXAMIANS APP