Building Construction Crown is located at None of these Highest point on the intrados of the arch Highest point on the extrados of the arch Skew-back of the arch None of these Highest point on the intrados of the arch Highest point on the extrados of the arch Skew-back of the arch ANSWER DOWNLOAD EXAMIANS APP
Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 12 24 25 18 12 24 25 18 ANSWER DOWNLOAD EXAMIANS APP
Building Construction Nogging of a common wooden partition is Upper horizontal wooden member Vertical wooden member Lower horizontal wooden member Intermediate horizontal wooden member Upper horizontal wooden member Vertical wooden member Lower horizontal wooden member Intermediate horizontal wooden member ANSWER DOWNLOAD EXAMIANS APP
Building Construction Weep holes are provided in retaining and breast walls To ventilate the stone masonry To add architectural beauty To drain off the water from the filling To increase compaction of the earth retained To ventilate the stone masonry To add architectural beauty To drain off the water from the filling To increase compaction of the earth retained ANSWER DOWNLOAD EXAMIANS APP
Building Construction The width of the hollow space between two walls of a cavity wall should not exceed 10 cm 5 cm 7.5 cm 15 cm 10 cm 5 cm 7.5 cm 15 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction In which of the following directions, the strength of timber is maximum? Perpendicular to grains Same in all directions Parallel to grains Perpendicular to grains Same in all directions Parallel to grains ANSWER DOWNLOAD EXAMIANS APP