MGVCL Exam Paper (30-07-2021 Shift 3)
Consider a solar PV plant with the following specific conditions:
Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 150 kWh/m²
Generator area of the PV plant: 10 m² Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 135 kWh
Calculate the performance ratio.

50%
75%
80%
60%

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
In transformers,
Statement 1: Deterioration of oil may occur due to the result of prolonged overloading of the transformer.
Statement 2: Dielectric faults occur in the winding due to turn-to-turn insulation breakdown.

Statement 1 is TRUE and Statement 2 is FALSE
Statement 1 is FALSE and Statement 2 is TRUE
Both Statement 1 and Statement 2 are FALSE
Both Statement 1 and Statement 2 are TRUE

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Determine the ohmic value of the current limiting reactor per phase external to a 40 MVA, 15 kV, 50 Hz, three phase synchronous generator which can limit the current on short circuit of 6 times the full load current. The reactance of the synchronous generator is 0.06 pu.

0.8 Ω
0.2 Ω
0.6 Ω
0.4 Ω

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Which of the following statements are correct?
(i) Advanced metering infrastructure (AMI) is typically more automated and allows real- time, on-demand interrogations with metering endpoints.
(ii) An Automated Meter Reading (AMR) device only communicates from the customer to the energy supplier.
(iii) AMR meters only provide kWh information and possible peak kW demand for the month.

(i) and (ii) only
(i) and (iii) only
(i), (ii) and (iii)
(ii) and (iii) only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP