Industrial Engineering and Production Management Break-even point is the point where Fixed and total cost lines intersect Variable and total cost lines intersect Sales revenue and total expensive lines intersect Fixed and variable cost lines intersect Fixed and total cost lines intersect Variable and total cost lines intersect Sales revenue and total expensive lines intersect Fixed and variable cost lines intersect ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Actual performance of a task is called A duration An event An activity None of these A duration An event An activity None of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The assumption in PERT is Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities Activities are fixed and can't be changed Cost of project will always be more than the estimated cost, if no timely corrections are taken A project will always be behind schedule, if left uncorrected A project can be subdivided into a set of predictable, independent activities Activities are fixed and can't be changed ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Positive slack on a PERT indicates that project is As per schedule Ahead of schedule Beyond schedule On critical path As per schedule Ahead of schedule Beyond schedule On critical path ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management At the break-even point, Total cost is more than the sales revenue Total cost is less than the sales revenue Total cost is equal to sales revenue Fixed cost is equal to variable cost Total cost is more than the sales revenue Total cost is less than the sales revenue Total cost is equal to sales revenue Fixed cost is equal to variable cost ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In crash program for a project indirect costs increase and direct costs decrease direct costs increase and indirect costs decrease cost is no criterion both direct and indirect costs, increase indirect costs increase and direct costs decrease direct costs increase and indirect costs decrease cost is no criterion both direct and indirect costs, increase ANSWER DOWNLOAD EXAMIANS APP