Surveying
After fixing the plane table to the tripod, the main operations which are needed at each plane table station are
(i) Levelling
(ii) Orientation(
iii) Centering
The correct sequence of these operations is

(ii), (iii), (i)
(i), (iii), (ii)
(iii), (i), (ii)
(i), (ii), (iii)

ANSWER DOWNLOAD EXAMIANS APP

Surveying
The prismatic compass and surveyor’s compass

give whole circle bearing (WCB) of a line and quadrantal bearing (QB) of a line respectively
both give WCB of a line
both give QB of a line and WCB of a line
both give QB of a line

ANSWER DOWNLOAD EXAMIANS APP

Surveying
In triangulation surveys

All listed here
The area is divided into triangular figures
Sides are not measured excepting the base line
Control stations are located from which detailed surveys are carried out

ANSWER DOWNLOAD EXAMIANS APP