Power Systems A thermal power plant is being supplied with coal having much more ash content than that for which it was designed. Which of its following units needs major modifications Ash handling unit. Cooling tower. Pulversing unit. Condenser. Ash handling unit. Cooling tower. Pulversing unit. Condenser. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Peterson coil is used in case of transmission line for increase the voltage level improve power factor reduce ferranti effect compensation of arcing grounds increase the voltage level improve power factor reduce ferranti effect compensation of arcing grounds ANSWER DOWNLOAD EXAMIANS APP
Power Systems For head and low discharge the water turbine used propeller turbine. Pelton wheel. Kaplan wheel. Francis turbine. propeller turbine. Pelton wheel. Kaplan wheel. Francis turbine. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A power generating station has a maximum demand of 1000 MW. The annual load factor is 75% and plant capacity factor is 60%. Calculate the reserve capacity? 1250 MW 500 MW 750 MW 250 MW 1250 MW 500 MW 750 MW 250 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems What should be the minimum depth (in metre)of cable trench to dug for laying of 1.1 kV? 0.90. 1.20. 0.75. 1.05. 0.90. 1.20. 0.75. 1.05. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which one of the following relays has the capability of anticipating the possible major fault in a transformer? Buchholz relay Differential relay Over current relay Over fluxing relay Buchholz relay Differential relay Over current relay Over fluxing relay ANSWER DOWNLOAD EXAMIANS APP