Industrial Engineering and Production Management A systematic job improvement sequence will consist of Job enrichment All of these Motion study Time study Job enrichment All of these Motion study Time study ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as Rowan Plan Taylor Differential Piece rate system Halsey Premium plan Day work plan Rowan Plan Taylor Differential Piece rate system Halsey Premium plan Day work plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The break-even point represents The time when unit can run without any loss and profit The time when company can make maximum profits The most economical level of operation of any industry Time when industry will undergo loss The time when unit can run without any loss and profit The time when company can make maximum profits The most economical level of operation of any industry Time when industry will undergo loss ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management In PERT analysis, critical path is obtained by joining events having -ve slack Zero slack +ve slack Dummy activities -ve slack Zero slack +ve slack Dummy activities ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Service time in queuing theory is usually assumed to follow Normal distribution Exponential law Erlang distribution Poisson’s distribution Normal distribution Exponential law Erlang distribution Poisson’s distribution ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Dummy activities are used to None of these Maintain the required net work Determine the project completion time Determine the critical path None of these Maintain the required net work Determine the project completion time Determine the critical path ANSWER DOWNLOAD EXAMIANS APP