Process Equipment and Plant Design A minimum clearance of about __________ mm is maintained between the distillation column wall and the bubble cap. 95 76 38 19 95 76 38 19 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The ratio of volumes of the mixed reactor to the plug flow reactor (for identical feed composition, flow rate, conversion, and for all positive reaction orders) is always 1 Equal to the order of reaction >1 < 1 1 Equal to the order of reaction >1 < 1 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In a shell and tube heat exchanger having square pitch, the shell side equivalent diameter is given by (where, P = pitch, d = outside diameter of the tube) 4(P² - πd²/4)/πd Πd/4P² (P² - πd²/4)/πd 4P²/πd 4(P² - πd²/4)/πd Πd/4P² (P² - πd²/4)/πd 4P²/πd ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design In case of bubble cap distillation column of diameter greater than 1.2 metres, the cap diameter is roughly about __________ cms. 20 35 30 10 20 35 30 10 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The force due to wind load acting on a tall vessel depends upon its Outside diameter Height All of these Shape Outside diameter Height All of these Shape ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Pick out the wrong statement pertaining to the design of the distillation column. The purpose of the slot is to disperse the gas into the liquid in the form of small bubbles None of these If sufficient slot area is not provided, the gas may pass through the skirt clearance Generally, a skirt clerance of 0.5" to 1.5' is recommended to prevent plugging of the slots by residue build up The purpose of the slot is to disperse the gas into the liquid in the form of small bubbles None of these If sufficient slot area is not provided, the gas may pass through the skirt clearance Generally, a skirt clerance of 0.5" to 1.5' is recommended to prevent plugging of the slots by residue build up ANSWER DOWNLOAD EXAMIANS APP