Power Systems A generating station has a maximum demand of 50 MW a load factor of 60 %, a plant capacity factor of 45 % and if the plant while running as per schedule were fully loaded. The daily energy produced will be 720 MW. 740 MW. 710 MW. 730 MW. 720 MW. 740 MW. 710 MW. 730 MW. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Counter poise is used for less surge impedance proper discharging of lighting surges reduce losses more surge impedance less surge impedance proper discharging of lighting surges reduce losses more surge impedance ANSWER DOWNLOAD EXAMIANS APP
Power Systems For flat voltage profile system, voltage regulation is 50% 100% 0% any of the above 50% 100% 0% any of the above ANSWER DOWNLOAD EXAMIANS APP
Power Systems IF the time of operation of a relay for unity TMS is 10 sec then the time of operation for 0.5 TMS is 20 sec. 5 sec. none of these. 10 sec. 20 sec. 5 sec. none of these. 10 sec. ANSWER DOWNLOAD EXAMIANS APP
Power Systems If the load is short circuited, then reflection coefficient of voltage is -2 0 -1 1 -2 0 -1 1 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Maximum power transfer capability of transmission line can be increased by Using bundled conductors All of these Parallel transmission lines Using series capacitance Using bundled conductors All of these Parallel transmission lines Using series capacitance ANSWER DOWNLOAD EXAMIANS APP