Power Systems Operating cost of thermal power station is less than that of nuclear power plant. less than that of diesel power plant. is the same as that of nuclear power plant. less than that of hydroelectric power plant. less than that of nuclear power plant. less than that of diesel power plant. is the same as that of nuclear power plant. less than that of hydroelectric power plant. ANSWER DOWNLOAD EXAMIANS APP
Power Systems When reactance grounding is used in network, the voltage between neutral and ground is IR0 × Xn both 1 and 3 IN × Xn 3×IR0 × Xn IR0 × Xn both 1 and 3 IN × Xn 3×IR0 × Xn ANSWER DOWNLOAD EXAMIANS APP
Power Systems The inertia constant of 100 MVA, 50 Hz, 4 pole generator is 10 MJ/MVA. If the mechanical input to the machine is suddenly raised from 50 MW to 75 MW, the rotor acceleration will be equal to 12.5 electrical degrees/s² 125 electrical degrees/s² 22.5 electrical degrees/s² 225 electrical degrees/s² 12.5 electrical degrees/s² 125 electrical degrees/s² 22.5 electrical degrees/s² 225 electrical degrees/s² ANSWER DOWNLOAD EXAMIANS APP
Power Systems Length of the cable is doubled, its capacitance C will be doubled. one-fourth. one-half. unchanged. doubled. one-fourth. one-half. unchanged. ANSWER DOWNLOAD EXAMIANS APP
Power Systems High capacity generators and motors are of star connected with grounding network any of the above star connected network delta connected network star connected with grounding network any of the above star connected network delta connected network ANSWER DOWNLOAD EXAMIANS APP
Power Systems An over current relay, having a current setting of 125% connected to a supply circuit through a current transformer of ratio 500/5. The plug setting multiplier for a fault current of 5 kA is 8 2 6 5 8 2 6 5 ANSWER DOWNLOAD EXAMIANS APP