Power Systems The angular moment of 10 MVA generator is 0.2. Find the new value of angular moment for 20 MVA base? 0.1 pu 0.4 pu 0.25 pu 0.2 pu 0.1 pu 0.4 pu 0.25 pu 0.2 pu ANSWER DOWNLOAD EXAMIANS APP
Power Systems A lossless power system has to serve a load of 250 MW. There are two generators(G1 and G2) in the system with cost curves C1 and C2 respectively defined as follows: C1 = PG1+0.055P²G1 C2 = 3 PG2 + 0.03 P²G2 Where PG1 and PG2 are the MW injections from generators G1 and G2 respectively. Thus, the minimum cost dispatch will be PG1 = 100 MW and PG2 = 150 MW PG1 = 150 MW and PG2 = 100 MW PG1 = 0 MW and PG2 = 250 MW PG1 = 250 MW and PG2 = 0 MW PG1 = 100 MW and PG2 = 150 MW PG1 = 150 MW and PG2 = 100 MW PG1 = 0 MW and PG2 = 250 MW PG1 = 250 MW and PG2 = 0 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems A hydro power plant of run off river type should be provided with pondage so that the firm capacity of plant is increased. operating head is controlled. pressure inside the turbine casing remains. kinetic energy of the running water is fully utilized. firm capacity of plant is increased. operating head is controlled. pressure inside the turbine casing remains. kinetic energy of the running water is fully utilized. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The shape of the disc of an induction disc relay is spiral. circular. elliptical. none of these. spiral. circular. elliptical. none of these. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a short circuit test circuit breaker, time to reach the peak re-striking voltage 60 microsecond & the peak re-striking voltage 120 kV. Determine average RRRV (Rate of rise re-striking voltage)? 1 × 106 kV / sec. 3 × 106 kV / sec. 3.5 × 106 kV / sec. 2 × 106 kV / sec. 1 × 106 kV / sec. 3 × 106 kV / sec. 3.5 × 106 kV / sec. 2 × 106 kV / sec. ANSWER DOWNLOAD EXAMIANS APP
Power Systems If the load is short circuited, then reflection coefficient of voltage is -2 1 -1 0 -2 1 -1 0 ANSWER DOWNLOAD EXAMIANS APP