Power Systems

Power Systems
If the time of operation of a relay for unity TMS is 10 sec. the time of operation of 0.5 TMS will be _______________ secs.

 3.
 7.
 20.
  5.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Hydro-graph is similar to

 mass curve.
 energy load curve.
  load curve.
 both B and C.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
In thermal power stations, economiser will

 reduce the thermal efficiency
 increase the thermal efficiency
 both 2 and 3
 reduce the heat

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Stability of a transmission line can be increased by

 series capacitor
 both 1 and 2
 shunt capacitor
 shunt reactor

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Capacitance voltage transformer ( CVT ) is used to

 connect instruments on the LT side.
 none of these.
 reduce losses in a transmission line.
  improve the power factor of the transmission.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Two generating stations delivering a powers of P1 = 150 MW, P2 =100 MW and the B coefficients are B11 = 0.005, B22 = 0.002, B12=B21= -0.001. Find the transmission line losses?

 102.5
 95.5
 105.2
 85.5

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑