If the time of operation of a relay for unity TMS is 10 sec. the time of operation of 0.5 TMS will be _______________ secs.

 7.
  5.
 20.
 3.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
In a long transmission line, if we increase the length of the line, the parameters A and B respectively

 decreases and increases
 decreases and decreases
 increases and decreases
 increases and increases

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
To prevent maloperation of deferentially connected relay while energizing a transformer, the relay restraining coil is biased with

 7th harmonic current.
  5th harmonic current.
 3rd harmonic current.
 2nd harmonic current.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Uses of diesel power stations

 standby plants.
  peak load plant.
  emergency plants.
All of these

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Find the value of a729, where "a" is the operator

 α²
 0
 α
 1

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A loss less transmission line has a length of 600 km, find the phase shift of voltage signal?

 90°
 45°
 42°
 36°

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑