Power Systems A generated station has a maximum demand of 30 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is 5 MW 6 MW 12 MW 10 MW 5 MW 6 MW 12 MW 10 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems A diesel power plant is generally used as a/an Standby/emergency plant. Peak loads. Any of above. Base load. Standby/emergency plant. Peak loads. Any of above. Base load. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Ferranti effect occurs under no load half load full load any of the above no load half load full load any of the above ANSWER DOWNLOAD EXAMIANS APP
Power Systems A transmission line has impedance of (0.005 + j0.05) pu. Find the line at which maximum value of negative DC off set current is produced, if it is applied with Vm sinωt? 9.68 msec 1.47 msec 4.68 msec 2.63 msec 9.68 msec 1.47 msec 4.68 msec 2.63 msec ANSWER DOWNLOAD EXAMIANS APP
Power Systems Out of the following plant categories which is not the base load power plant? Run of river. Pump storage. Nuclear. Diesel. Run of river. Pump storage. Nuclear. Diesel. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A power station has a maximum demand of 15000 kW. The annual load factor is 50% and plant capacity factor is 40%. What is the reserve capacity of the plant? 6000 kW 3000 kW 3750 kW 7500 kW 6000 kW 3000 kW 3750 kW 7500 kW ANSWER DOWNLOAD EXAMIANS APP