MGVCL Exam Paper (30-07-2021 Shift 3)
A 50 Hz synchronous generator is connected to an infinite bus through a line. The p.u. reactances of generator and the line are j0.4 p.u. and j0.2 p.u. respectively. The generator no load voltage is 1.1 p.u. and that of infinite bus is 1.0 p.u. The inertia constant of the generator is 4 MW-sec/MVA. Determine the frequency of natural oscillations if the generator is loaded to 60% of its maximum power transfer capacity and small perturbation in power is given.

1.2 Hz
1.8 Hz
0.8 Hz
1.6 Hz

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
A 10 A, Type C Miniature Circuit Breaker (MCB) will trip at fault currents

less than 10 A
between 10 A and 50 A
between 50 A and 100 A
greater than 100 A

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Match the following shown in table

A = (iii), B = (ii), C = (i)
A = (ii), B = (i), C = (iii)
A = (ii), B = (iii), C = (i)
A = (iii), B = (i), C = (ii)

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 3)
Which of the following statements are correct?
(i) Advanced metering infrastructure (AMI) is typically more automated and allows real- time, on-demand interrogations with metering endpoints.
(ii) An Automated Meter Reading (AMR) device only communicates from the customer to the energy supplier.
(iii) AMR meters only provide kWh information and possible peak kW demand for the month.

(i) and (ii) only
(ii) and (iii) only
(i), (ii) and (iii)
(i) and (iii) only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP