Irrigation Engineering
While deciding the alignment of a proposed canal taking off from a river at B, three alignments of approximately equal lengths are available. These cross a drainages at C1, C2 and C3 where drainage bed levels C1 > C2 > C3, you will provide at site C3

A syphon aqueduct
A super passage
An aqueduct
A syphon

ANSWER DOWNLOAD EXAMIANS APP

Irrigation Engineering
A hydraulic jump is generally formed when a stream moving with

A hyper-critical velocity meets a stream moving with a sub-critical velocity
A hyper-critical velocity meets a stream moving with a critical velocity
A hyper-critical velocity meets a stream moving with a hyper-critical velocity
A sub-critical velocity meets a stream moving with a hyper-critical velocity

ANSWER DOWNLOAD EXAMIANS APP